Cost of Analysis – Matthew King
Description | Estimate | Actual | Date | Give |
---|---|---|---|---|
Business License | $325.00 | |||
Permits | $1,420.00 | |||
Builders Risk Insurance | $2,700.00 | |||
General Liability | $650.00 | |||
Temporary Utilities | $500.00 | |||
Stakeout Survey | $800.00 | |||
Portolet | $500.00 | |||
Dumpster | $2,300.00 | |||
Equipment Rental | $4,000.00 | |||
Lot Clearing | $4,800.00 | |||
Sewer Tap Fee | $3,400.00 | |||
Fill Dirt | $4,200.00 | |||
Foundation & Footings | $22,000.00 | |||
Framing Labor | $47,000.00 | |||
Framing Materials | $103,000.00 | |||
Plumbing Labor | $17,000.00 | |||
Plumbing Fixtures | $5,800.00 | |||
HVAC | $14,500.00 | |||
Interior Doors & Labor | $3,600.00 | |||
Electrical /Light Fixtures | $2,500.00 | |||
Electrical Labor | $14,100.00 | |||
Hardware & Mirrors | $500.00 | |||
Appliances | $4,500.00 | |||
Insulation Walls & Ceiling | $11,300.00 | |||
Drywall Materials | $7,100.00 | |||
Drywall Labor | $7,300.00 | |||
Trim Work Materials & Labor | $4,400.00 | |||
Painting Materials & Labor | $17,000.00 | |||
Flooring | $18,000.00 | |||
Cabinets | $11,000.00 | |||
Countertops | $8,000.00 | < |